Project File grows abnormally

V

VP

Hi,

I have a project file which grows abnormally and total tasks less than 110.

No Template to build the schedule, No Custom fields, Notes fields are there.

Any pointer is appreciated.

VP
 
J

John

VP said:
Hi,

I have a project file which grows abnormally and total tasks less than 110.

No Template to build the schedule, No Custom fields, Notes fields are there.

Any pointer is appreciated.

VP

VP,
You most likely have file corruption and/or bloat. Go to our MVP website
at, http://www.mvps.org/project/faqs.htm, and take a look at FAQ 43 -
Handling project file corruption and/or bloat.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top