Hi,

I have the following problem: I have project managers who
are also assigned to other project as resource. The
problem now is that these project managers can now also
change all the project they are on as resource even these
project where they should not have project manager access.

Anyone an idea how I can solve this?

Thanks!

Kenneth
 
E

Ethan

One method that I have used in the past is to create a category that
contains a project or projects and in the category permissions for a
user or group deny "Save a Project" permisson. This has the effect of
only allowing read-only access to those projects.

But there is an admin overhead of making sure those projects are
included in the category.

Ethan Dorfman