troy_lee
I have a simple plan that I am putting together for a garden. I have
set the working time to a copy of the 24 hour calendar with start and
end times of 12:00 AM and 12:00 PM. I have changed the Project to
ensure that it is using this copied calendar.
I have one task that starts the project (milestone). I am using this
date as the only constrained date. Everything else is being set up to
start as soon as possible. I am setting up three tasks in a set as 0
day durations (milestones). I am using a FS logic with a lag to link
the tasks. The problem is that I am getting screwy dates. For
instance, a lag of 7 days only gives me three days of scheduled time
on the Gantt.
Any suggestions.
Thanks.
Troy
set the working time to a copy of the 24 hour calendar with start and
end times of 12:00 AM and 12:00 PM. I have changed the Project to
ensure that it is using this copied calendar.
I have one task that starts the project (milestone). I am using this
date as the only constrained date. Everything else is being set up to
start as soon as possible. I am setting up three tasks in a set as 0
day durations (milestones). I am using a FS logic with a lag to link
the tasks. The problem is that I am getting screwy dates. For
instance, a lag of 7 days only gives me three days of scheduled time
on the Gantt.
Any suggestions.
Thanks.
Troy