Project Plan Maintenance: Best Practices

R

Rebecca Culver

We are struggling with the best way to maintain our larger project
plans.

Time is charged to the project plans via PWA timesheets, and then
accepted by the PM.

We'd like to extend the duration for a partially completed task that
wasn't finished on schedule, in order to avoid setting a hard
constraint on the finish date. However, we've found this wreaks havoc
on the remaining hours on the task.

We are testing the Update Project/Reschedule uncompleted work to
start.. option. Wondering if anyone else has recommendations, or has
used this command -- especially for larger projects??

Thanks!
 