A
Abi
Hi we recently implemented Project Server 2003 and we use Project Pro 2002 to publish our projects. It's only been a month and we've ecnountered the issues outlined below. I hope anyone of you could help me out:
1) Transferring ownership to another Project Manager does not totally transfer complete ownership. For example Manager A publishes the project, but later on it gets transferred to Manager B. Editing the project fields allows you to transfer ownership, but Manager A still gets the notifications that are meant for Manager B.
2) Timesheet Approval link in PWA cannot be found even if it is set in the Menu settings under Admin and the account is already set to Administrator -- all access.
3) Sometimes when projects get published, Project Server fails to create a WSS project site. Therefore there is no document repository.
4) Baseline costs appear to be zero in PWA 2003 after saving the baseline costs in project pro 2002.
1) Transferring ownership to another Project Manager does not totally transfer complete ownership. For example Manager A publishes the project, but later on it gets transferred to Manager B. Editing the project fields allows you to transfer ownership, but Manager A still gets the notifications that are meant for Manager B.
2) Timesheet Approval link in PWA cannot be found even if it is set in the Menu settings under Admin and the account is already set to Administrator -- all access.
3) Sometimes when projects get published, Project Server fails to create a WSS project site. Therefore there is no document repository.
4) Baseline costs appear to be zero in PWA 2003 after saving the baseline costs in project pro 2002.