Project Pro 2007 task start date

K

Kerry

We're running with Project Server. I don't know that it makes a difference. I
have a PM that is starting a plan, her first plan. Whenever she attempts to
add a task it's fine until she add a resource. Then it changes the start date
to sometime out in 2012. I can open her plan and create a task, and assign a
resource and the start is 7/29/2009. When I view it, the entire plan looks
fine. It ends in 2009. When she opens it, it end 2013. Any suggestions? I'm
stumped.
 
M

Mike Glen

Hi Kerry,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top