I'm scheduling a task in pr. professional 2003.
I've 80 h of work and 3 resources assigned (work divided
equally between all resources). All of them with 100%
units.
Then I add another resource to the task, this one with a
different working calendar. I wish project would divide
the total work equally between all 4 resources, but
instead it assigns different hours to resources that have
different calendars.
I'm working with fixed work.
How does project calculates the assignments?
I can't understand it
Help Please
Jose
I've 80 h of work and 3 resources assigned (work divided
equally between all resources). All of them with 100%
units.
Then I add another resource to the task, this one with a
different working calendar. I wish project would divide
the total work equally between all 4 resources, but
instead it assigns different hours to resources that have
different calendars.
I'm working with fixed work.
How does project calculates the assignments?
I can't understand it
Help Please
Jose