Project Server 2007 and Outlook Plugin

B

bryan andrews

Hi,

I am trying to see how the different settings for timesheets affects the
outlook form.For example, when making the timesheet show billable and
non-billable time in Project Server settings... I cannot see any changes to
thh outlook task timesheet view.

I have tried deleting the tasks and reloading them. Is there a trick to
seeing the changes?

Also the outlook help file for the addin mentioned different views depending
on how project server was setup (combining task and timesheet views) but i
cannot seem to make any different display in outlook though i have changed
settings in "Task Settings and Display > Tracking Method" and "TimeSheet
Settings and Default > Outlook Display".

Do i have to refresh a form in outlook when this changes?

Thanks!
 
R

Rob

Hi Bryan,
Are you looking at a previously created timesheet, or are these changes not
being reflected in a freshly created timesheet?
 
B

bryan andrews

The only way i can get the "new format" to show in the outlook custom form
is to uninstall and reinstall the outlook addin (after changing the setting
on the project server).

Thanks.
 
Top