Project Server 2007 - Difference from Total Work and Timephased Wo

C

Carlo Rosmini

We use a day of 7,5h in our Project Server 2007 system. We make a project
with project professional and create a task of 1 day and associate a resource
at this task. If we go in "my task" page of the rosurce we can see in the
progress column a duration of 0,938d. This is not right, we want see 1d. If
we click on the task, i can see the details : Total Work = 1d , Timephased
Work = 0,94d.
Which is the difference of these two works ? How we can use the same scale ?

Thanks in advance
Carlo
 