Project server 2007 - displayed unit

L

Laurent

Hello,

I use project server 2007 and PWA and I would like to display the
information in day and not in hours. For example, the view assignment is
not very cleat with hours. 81 days is more clear than 648 hours...

Any idea ?

Thanks in advance

Laurent
 
B

Ben Howard

Hi, in the standard PWA views you cannot change these fields, you are stuck
with hours.
If you are viewing data from the OLAP cube, you could insert a calculated
field which divides your hours by 8 to give days.
 
Top