Project Server 2007 Timesheets

S

shan

Hi!,

How do it turn on the timesheet feature in project server 2007?

How could I master the timesheet module?

Any document or reference will be greatly appreciated!

Many Thanks!
Shan
 
D

Dale Howard [MVP]

Shan --

By default, the Timesheet functionality is enabled in Project Server 2007.
Before anyone can use this functionality, however, your Project Server
administrator must create Timesheet Periods representing your organization's
reporting requirements for project, non-project, and non-working time.
Generally, these Timesheet Periods are one week at a time. Then, your users
must create a Timesheet for the current time period from the My Timesheets
page in PWA, report their time, and submit it to their timesheet approver
for approval. If you want to master the setup of Project Server 2007 as
administrator, or master how to use the system as a project manager, you
might consider purchasing our company's books on Project Server 2007,
available for purchase at:

http://www.projectserverbooks.com

Hope this helps.
 