We are using project server 2007. In timesheet eventhough the task
finish date is passed, the reaource can able to book their timings againest
that task by adding the the task lines from Add Lines button. How can I
disable the this.

Thanks in advance,
Arun
 
D

Dale Howard [MVP]

Arun --

The project manager can close the task to further updates if the task is
completed. He/she can log into PWA, click the Server Settings link in the
Quick Launch menu, and then click the Close Tasks to Update link. This will
prevent the team member from adding any more time to the already-completed
task. Hope this helps.
 