Project Server - Budgeted completed % of a Project

C

Cristian

Hi,

I need to know if there is a way to know the budgeted % completed for a
project published in Project Server 2007. If i set a baseline for the project
i suposed that project server could retrieve that information on a daily
basis.

Any help will be needed.

Regards.
 
A

Andrew Lavinsky

I am not sure I understand entirely, but I think you could get the data by
creating a custom field using the formula BCWS/Baseline Cost..... It would
update to whatever you set the Status Date for. You could also export it
to Excel as timephased data.
 