Project Server Edits Done on the Web

N

Nathan Kimpel

Is there a way to edit a task and change the start date or
end date from the web or is the project file itself the
only source of admin changes?
 
R

RonSo

A resource cannot change the start, duration, and end dates of a task. However, they CAN change the remaining work to 0, (therebye causing the task to show 100% complete) and I think they can set their assignment (as opposed to task) finish date. This is all a little strange because some resources may be allowed to create completely new tasks. I am guessing that MSFT allowed this because when a resource creates a task, there is only one resource on that task and there would be no task level conflicts.
 