Hello ,

Can you help me with following question :
In MSPServer I can see RBS value ( always -1 ) . Is it
possible to change the RBS value ( may be by Visio 2002
or some other visual tool ) , if it is unpossible what is
the reason of RBS visualisation ?

Thank you,
Arkady .
 
J

Jim Snider

The minus 1 shows up because an RBS has not yet been
defined. You have to define the reserved RBS enterprise
field in the global template and then create the lookup
table. (This is not a simple task that is easily explained
here.)

After this is done, you can assign the appropriate RBS
value to each resource by using the edit feature in the
Resource Center.

Jim
 