[Project Standard 2010] Display the WBS index beside names

R

Robert

Hello,
In the 2010 Standard version, where/how can we display/remove the WBS index
besides the tasks names?
Thanks
 
D

Dale Howard [MVP]

Robert --

From your question, I assume you are seeing the outline number, such as
1.2.3, to the left of each task name. Assuming this is the case, click the
Format tab and then deselect the Outline Number checkbox in the Show/Hide
section of the Format ribbon. Hope this helps.
 