Hi Dale -
Thanks.... this is for a new client of mine. Just found out that as part
of a problem solving effort, they removed the field and then re-added it back
to Global. each project just needs to be re-published to get the indicators
back. Wish there was a way to "mass publish" a project as every project is
affected....
By the way, did Gary share with you my email about the "Merchant" field on
the receipt that was handed out at the MSP Conference?
--
Thanks much!
Randy
Dale Howard said:
RandyK --
Before you waste too much time on this issue, open any project in Project
Professional 2007, press the F9 function key to recalculate the project, and
then save the project and click File - Publish. Does the Project Status
information show up for that newly-published project in the Project Center?
Let us know.