OK, I have been dealing with this problem for a long time now. Whenever I
level the whole project, the tasks for each programmer do not level
correctly. Some tasks appear to be finishing out in 2007. Also, it appears
that whenever a programmer books time to a task in Web Access without marking
the task as complete, it throws there whole schedule off because the task
will have a much later finish date. Any reason why this is happening? Can
anybody give me the correct answer to correct this problem? I would really
appreciate your help. Thanks!
level the whole project, the tasks for each programmer do not level
correctly. Some tasks appear to be finishing out in 2007. Also, it appears
that whenever a programmer books time to a task in Web Access without marking
the task as complete, it throws there whole schedule off because the task
will have a much later finish date. Any reason why this is happening? Can
anybody give me the correct answer to correct this problem? I would really
appreciate your help. Thanks!