OK, I have been dealing with this problem for a long time now. Whenever I
level the whole project, the tasks for each programmer do not level
correctly. Some tasks appear to be finishing out in 2007. Also, it appears
that whenever a programmer books time to a task in Web Access without marking
the task as complete, it throws there whole schedule off because the task
will have a much later finish date. Any reason why this is happening? Can
anybody give me the correct answer to correct this problem? I would really
appreciate your help. Thanks!
 
B

Bill

Brett,

I don't know if this will solve your problem but it helps me make sure your
problem does not happen. First, set your filter on your project professional
to fileter by resource. Next, check to see if the predecessor looks correct.
Sometimes when you get into larger projects and you change resources around,
you can't see the predecessor conflict. Next look at the task information
and make sure it is set to fixed work and the constraint type is set to "as
soon as possible". Sometimes the project may default to another setting.

I hope these tips help