Hello all,

The Project Summary Task in PPro|Tools|Options does not apply to a
new/blank projects. I think that you can set this to show by default
via the registry. Does anyone know how?

Your help will be much appreciated.

Thanks!
 
D

Dale Howard [MVP]

Nogol --

To the best of my knowledge, I do not believe there is a registry setting
that controls this, nor is there a Set as Default option on the View page of
the Options dialog to force the Project Summary Task to display. Because of
this, I would recommend that you simply train everyone to apply it in every
new project, or that you write a macro that will display it in one click.
To help your PM's with this issue, I would recommend that you apply the
Project Summary Task in every existing company template. Hope this helps.
 