Project Summary - Urgent! please

  • Thread starter project summary task---Urgent! please
  • Start date
P

project summary task---Urgent! please

Hello! Everyone:

I have a requirement to change the Project summary bar to refect the progress.

Example: Project 1 -- Start date of 01/01/2005 and EndDate of 06/01/2005
with having only 20% complete.

When you see the Project summary bar style will show as 01/01/2005 -
06/01/2005. How to reflect the balance 80% of work and then the change finsh
date in the bar.

Please provide me an answer . I need this very urgent!

Regards,
Sankar,PMP
 
Top