I have a question
Does anybody know how, once I have several projects into project server, view how much time each resource has assigned to each project? I guess this is a necessary task in many enterprises..

Thanks in advanc

JR Barrius
 
K

Kasper Ovi

Hi

Select the Resources menu, then select the resource you want to view
assignments for, and click "View availability". From this screen, choose the
view "view work assignment by project" (or something similar, the second one
on the list).
Then you'll see how much your resource uses on different projects.

Another way is to use OLAP Analysis views, if you want more detail and for
more resources at one time.

Good luck.