B
bnix
Hello Everyone,
We are looking at upgrading to MS Project 2007 and I had a question
from a few of our PM's on a task question that I am hoping some of you
may be able to provide insight to.
Is it possible to have a task that must be completed on a particular
day, to be automatically rescheduled to that next designated day in
the event a predecessor task runs over?
In our case, change management must be entered on a Tuesday for any
production items, so if a task that must be completed before the
change management request is entered on a Tuesday, runs over and
causes the CM task to miss that Tuesday, can it reschedule itself to
the following Tuesday?
This is probably not so much a 2007 question as an overall question
and we are currently using Project 2003.
Let me know if additional information is needed.
I appreciate any insight that may be given.
Thanks,
Bruce
We are looking at upgrading to MS Project 2007 and I had a question
from a few of our PM's on a task question that I am hoping some of you
may be able to provide insight to.
Is it possible to have a task that must be completed on a particular
day, to be automatically rescheduled to that next designated day in
the event a predecessor task runs over?
In our case, change management must be entered on a Tuesday for any
production items, so if a task that must be completed before the
change management request is entered on a Tuesday, runs over and
causes the CM task to miss that Tuesday, can it reschedule itself to
the following Tuesday?
This is probably not so much a 2007 question as an overall question
and we are currently using Project 2003.
Let me know if additional information is needed.
I appreciate any insight that may be given.
Thanks,
Bruce