I have a Project Manager who has just published an ADMINISTRATIVE PROJECT for
all of her groups Support & Maintenance activities (in the IT Division).

The email notification sent out from Project Server 2003 to her resources
shows the correct TASK START DATE - but the FINISH DATE is incorrect.

I have verfied that she has the CORRECT DATES both in the acutall PUBLISHED
project plan and the WEB VIEW of her project.

Is this a BUG?

Is there somthing that I check to see where the email notifications for task
assignments are getting their dates from?

Any assistance would be greatly appreciated.

Thank You.

Ivor

P.S. - We are running MS Project Server 2003 with Project Professional 2003
and SQL Server 2000.
 