Project Tasks Not Appearing in Timesheets

J

Jonathan H

Hello,

I reckon this one must be user error, but I can't see what I'm doing wrong.

When I create a new timesheet, only administrative time is displayed. If I
want to get the Project Tasks to display, I have to Add Lines.
I thought the only way to do this was to set the default Timesheet to No
Population, but this is not the case. It is set to Current Task Assignments.

What else could I have changed on the system to cause this behaviour?

Kind Regards,

Jonathan
 
P

/pd

Try deleteing the timesheet and recreating it. This should now display all
the tasks that you have updated duriong that period.

/pd
 
J

Jonathan H

Yep, tried that. No joy I'm afraid.

/pd said:
Try deleteing the timesheet and recreating it. This should now display all
the tasks that you have updated duriong that period.

/pd
 
D

Dale Howard [MVP]

Jonathan --

When you create a Timesheet, the system displays only those tasks scheduled
during that week. Do you actually have tasks scheduled during that week?
If not, they won't appear, but you can add tasks scheduled in the future by
using the Add Lines feature. Let us know.
 
J

Jonathan H

Hi Dale,

Yep, there are tasks scheduled during that week. Two of them in fact.

If I go to the Resource Centre and View Assignments I can see them plain as
day.

Thanks for getting back to me. Currently in the process of going through
your Managing Enterprse Projects book. Think I need the admin one as well
though...

Cheers,

Jonathan
 
Top