Juliana Giorni said:
Hey Julie!
Yes! I wanna see that prompt pop up.
WHen I insert a new task, for example, I assume that this prompt pop
up appear when I try to link this new task with another, for
examplo,
to alert me that the link between tasks might change after that.
Regards
Juliana
Hello Juliana,
The prompt will only pop up if you *don't* link the task and try to
either enter a start date for the new task which is close to the
finish date of the task above, or if you try to drag the task in the
Gantt chart view until it is close to the finish of the task above.
Be aware that by default, if you insert a new task between two tasks
that are linked in a Finish to Start relationship, Project will
automatically link them, so that may be why you aren't seeing the
prompt -- they are already linked. I recommend that the option
"Autolink inserted or moved tasks" on the Schedule tab of the Options
dialog box be shut off. Then when you insert a new task -- it will
never link and it's up to you to decide what you want to do.
Try this, create a simple project with two tasks. Do not link the two
tasks. Drag the Gantt bar for the second task until it is close to
the end of the first task -- does the prompt appear?
Julie