J
JB
My PM is telling me that one of his resources through PWA updated 4 tasks.
He said that when he accepted the upates in PWA, about 20 other tasks that
did belong and did not belong to that resource were changed as well. Why
would this happen? We are using Project Server 2003.
He said that when he accepted the upates in PWA, about 20 other tasks that
did belong and did not belong to that resource were changed as well. Why
would this happen? We are using Project Server 2003.