Hey Folks,
I currenty have a published workplan which is baselined. Out PMO has
restructured the template so I will have to make major changes to the
workplan. My intentions are to save locally as a mpp file, make the changes,
delete the old project and save and publish the new one. What affect will
this have on baseline as well as the progress reported (thru time tracking)
on the existing published workplan. Is the a more structure process to make
drastic changes to an existing published workplan.