Project Versions

T

TroyS

Does a project version (other than .Published) impact Resource Availability?

In otherwords, do only the .Published projects impact a resources
availability?

OR if i put in a .Published and a .Snapshot into project server, will the
availability be lessen/reduced by BOTH the .Published file and the .Snapshot
file?

I haven't been able to find this in the Project Server Guides (admin,
Configuration, etc) so if this is documented somewhere, please let me know
as well.

thx.
 
D

Dominic Moss

Troy,

Only the published version actually impacts on the availability of Resources
in the Enterprise Resource Pool. Versions allow you to run "what if?"
scenarios or to retain a snapshot of a project plan at a specific point in
time. You can use Versions in "Portfolio Modelling" - there are different
views as to the value of this feature.

--
Dominic Moss

www.projectability.co.uk

Helping people achieve more with Microsoft Project