Project View Does Not Show All Tasks

D

Devon Manelski

In the Views Projects In Project Center and click on a project it is
only showing 27 tasks when I have 47 in my actual project plan. I
have tried re-publishing assignments but they still don't appear.

What do I need to do to make it re-synch?

Thanks,
Devon
 
D

Dale Howard

Devon --

It sounds like your project in Microsoft Project Professional and your
project in PWA are "out of synch." To synch them up, click Collaborate -
Publish - Project Plan or Collaborate - Publish - All Information. Either
method should do the job for you. Hope this helps.
 
K

Kevin Flanagan

The default view is for My Tasks, so you may need to
change it to show all tasks.

Kevin
 
Top