AnneO
Again I have been directed here from the general discussion group. I am
trying to run my resource reports tracking the start and end time of those
resources by week, month and year.
In project 2003, I use a fixed duration and the calendar for
calculations so that I can run through a 7 day week. When I view this data
in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Assignment Reports I am unable to return
those same dates. It appears that any project that begins or ends on a
Saturday or
Sunday is truncated to the 5 day work week.
Any help would be greatly appreciated.
Thanks.
Anne
trying to run my resource reports tracking the start and end time of those
resources by week, month and year.
In project 2003, I use a fixed duration and the calendar for
calculations so that I can run through a 7 day week. When I view this data
in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Assignment Reports I am unable to return
those same dates. It appears that any project that begins or ends on a
Saturday or
Sunday is truncated to the 5 day work week.
Any help would be greatly appreciated.
Thanks.
Anne