Project Web Access - Calendars and durations

A

AnneO

Again I have been directed here from the general discussion group. I am
trying to run my resource reports tracking the start and end time of those
resources by week, month and year.

In project 2003, I use a fixed duration and the calendar for
calculations so that I can run through a 7 day week. When I view this data
in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Assignment Reports I am unable to return
those same dates. It appears that any project that begins or ends on a
Saturday or
Sunday is truncated to the 5 day work week.

Any help would be greatly appreciated.

Thanks.

Anne
 