projectserver2003 / enterprisecostfields

S

Sandro Dadaczynski

hi @all,

is it possible to create more then 10 enterprisecostfields in ms
projectserver 2003 how can i use in ms project 2003 pro?????
 
E

Ed Morrison

Projects, tasks, and resources each have only 10 Enterprise Cost fields
available. There are 40 Enterprise Number fields for each object that you
could also utilize.
 
S

Sandro Dadaczynski

but i need more then 10 enterprisecostfields :-/
is iz possible to create my own enterprisecostfields???

sandro
 
Top