We are having a problem where there is a discrecpancy between the Actual Work
and the Protected Actuals fields for certain tasks in a major project we are
working on.
I have been tasked with finding out how we can get these two columns back
into balance.
We are using managed time period. We recently upgraded to the latest
service pack. (Sp2a)
Further description of the problem. In this major project, we have a series
of tasks that have no resource assignments. The actual work field shows
Zero work (which is correct). The protected actuals field for certain tasks
is showing work in certain tasks. With some, it is even showing work before
the official start date of the project.
Any suggestions would be appreciated very much.
Regards,
Kevin Brezina
and the Protected Actuals fields for certain tasks in a major project we are
working on.
I have been tasked with finding out how we can get these two columns back
into balance.
We are using managed time period. We recently upgraded to the latest
service pack. (Sp2a)
Further description of the problem. In this major project, we have a series
of tasks that have no resource assignments. The actual work field shows
Zero work (which is correct). The protected actuals field for certain tasks
is showing work in certain tasks. With some, it is even showing work before
the official start date of the project.
Any suggestions would be appreciated very much.
Regards,
Kevin Brezina