J
Jonathan H
Hello,
Not a technical query here, but a question on how people do this currently.
Imagine the scenario:
1 Project exceeds the tolerances for it as laid down by the project
executives
2 Project Manager flags this up and escalates to the project executives
3 Project executives want to see the options to bring the project back on
track
4 Projct Manger goes away and creates a few versions of the plan that maybe
accept the overspend but deliver on time, or deliver on cost but with reduced
functionality etc.
5 Project executives review the plans, pick one, and the Project Manager
replaces the existing project plan with the new exception plan.
My questions are: How do I implement this? I'm not sure how to do the
'what-if' scenarios that allow me to see the impacts of various different
strategies on the resource pool.
Finally, when I replace the original project with the new project I want to
preserve actuals, etc. Is this all achieved simply by saving the exception
plan out as a file, and then back into Project Server with the same name as
the plan you want to replace?
I'm interested to hear your points of view on this. Seems like this type of
activity is pretty standard, but I'll be honest, I have no idea how to do it!
Thanks,
Jonathan
Not a technical query here, but a question on how people do this currently.
Imagine the scenario:
1 Project exceeds the tolerances for it as laid down by the project
executives
2 Project Manager flags this up and escalates to the project executives
3 Project executives want to see the options to bring the project back on
track
4 Projct Manger goes away and creates a few versions of the plan that maybe
accept the overspend but deliver on time, or deliver on cost but with reduced
functionality etc.
5 Project executives review the plans, pick one, and the Project Manager
replaces the existing project plan with the new exception plan.
My questions are: How do I implement this? I'm not sure how to do the
'what-if' scenarios that allow me to see the impacts of various different
strategies on the resource pool.
Finally, when I replace the original project with the new project I want to
preserve actuals, etc. Is this all achieved simply by saving the exception
plan out as a file, and then back into Project Server with the same name as
the plan you want to replace?
I'm interested to hear your points of view on this. Seems like this type of
activity is pretty standard, but I'll be honest, I have no idea how to do it!
Thanks,
Jonathan