Mike Mahoney
On My task page I display Work, Actaul Work(Progress) and Remaining Work. I
can choose to change display format to days or hours.
Drilling down to the detail form displays Work and Actaul Work in days, but
displays Remaining work in hours.
Updating the Task form by entering "5" in any of the columns (irregardless
of the display format) results in 5 hours Work, 5 days Actual Work and 5
hours Remaining Work.
So take care how you enter actuals as it messes up your planning a lot.
So as an improvement request lets have some consistency.
Mike
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...79bb3da2b8&dg=microsoft.public.project.server
can choose to change display format to days or hours.
Drilling down to the detail form displays Work and Actaul Work in days, but
displays Remaining work in hours.
Updating the Task form by entering "5" in any of the columns (irregardless
of the display format) results in 5 hours Work, 5 days Actual Work and 5
hours Remaining Work.
So take care how you enter actuals as it messes up your planning a lot.
So as an improvement request lets have some consistency.
Mike
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...79bb3da2b8&dg=microsoft.public.project.server