PS 2007 timesheet

A

Arun

Hi,
We are using project server 2007. Our resources are working in multiple
countries. So their working days will vary, like Sunday to Thursaday or
Monday to Friday. Cournetly our timesheet showing Friday and Staturday grayed
for all resources. I want to change Saturday and Sunday should be grayed for
some resource timesheet. How can I do that?

Thanks in advance,
arun
 
D

Dale Howard [MVP]

arun --

Even though the weekends are shaded in gray, they are not "grayed out" in
functionality. Users can still enter time on a Saturday or Sunday as
needed. Hope this helps.
 