PS07 - My Tasks - Tasks Gantt View

T

TroyS

in PS07 PWA, My Tasks - Go To - Tasks Gantt View

The Tasks Gantt View is greyed out and i can't find which view this is and
which Security Category turns this on?
Why would this be greyed out? I've not been changing permissions

Is this view the Resource Assignments - Summary view under Manage Views?
 
P

Paul Conroy

You need to turn on this feature

PWA > Server Settings > Task Settings & Display > Enable ActiveX Gannt view
for all user.
 
T

TroyS

that setting is turned on, yet it is still greyed out.
any ideas? perhaps in security groups?
 
P

Paul Conroy

Assuming the user get get to the task center then there are no other
permissions.

Check the PWA URL is in the trusted site zone.

If you lock down PWA, then the activex controls will need to be deployed
manually.
 
Top