PS2007 - Adding tasks on PWA doesn't update Project Plan

  • Thread starter Gustavo Holloway
  • Start date
G

Gustavo Holloway

Users are adding tasks and submiting for aproval but even after approval the
added tasks don't show on the Project Plan. Users can see these tasks on "My
Tasks". Any idea why this is not been sysnchronized?
 
G

Gustavo Holloway

No They weren't. After Republishing I see the tasks updated. So is this the
way it should work, after approving is necessary to republish the project?
 
Top