PS2007 - Earned Value in Data Analysis

T

TroyS

I want to show all of the std earned value calcluations in Data Analysis but
i'm not seeing those calculations available in the Totals of
MSP_Portfolio_Analyzer cube and I don't see it any of the other
NonTimephased cubes.

I know that Project Center has Earned Value and that if i drill into a
Project, I can see the Earned Value at the Task Level.

I wish to do this in Data Analysis as i want to graph such items as BCWS,
BCWP, ACWP and Budget and i want to expand/collapse a project to see tasks
names.

I want to show without having to create a manual calc: SPI, CIP, SV, CV,
Physical % Complete, Budget, BCWS, ACWP, BCWP

How do i get these values to populate the Data Analysis OLAP cube? Any ideas
or directions to links are welcomed...thx.
 
M

Mahmud K.

I'm facing the same problem right now, hope there are someone who will help us.



TroyS wrote:

PS2007 - Earned Value in Data Analysis
21-Apr-08

I want to show all of the std earned value calcluations in Data Analysis but
i'm not seeing those calculations available in the Totals of
MSP_Portfolio_Analyzer cube and I don't see it any of the other
NonTimephased cubes

I know that Project Center has Earned Value and that if i drill into a
Project, I can see the Earned Value at the Task Level

I wish to do this in Data Analysis as i want to graph such items as BCWS,
BCWP, ACWP and Budget and i want to expand/collapse a project to see tasks
names

I want to show without having to create a manual calc: SPI, CIP, SV, CV,
Physical % Complete, Budget, BCWS, ACWP, BCW

How do i get these values to populate the Data Analysis OLAP cube? Any ideas
or directions to links are welcomed...thx.

Previous Posts In This Thread:

PS2007 - Earned Value in Data Analysis
I want to show all of the std earned value calcluations in Data Analysis but
i'm not seeing those calculations available in the Totals of
MSP_Portfolio_Analyzer cube and I don't see it any of the other
NonTimephased cubes

I know that Project Center has Earned Value and that if i drill into a
Project, I can see the Earned Value at the Task Level

I wish to do this in Data Analysis as i want to graph such items as BCWS,
BCWP, ACWP and Budget and i want to expand/collapse a project to see tasks
names

I want to show without having to create a manual calc: SPI, CIP, SV, CV,
Physical % Complete, Budget, BCWS, ACWP, BCW

How do i get these values to populate the Data Analysis OLAP cube? Any ideas
or directions to links are welcomed...thx.


Submitted via EggHeadCafe - Software Developer Portal of Choice
Changing WCF Service Implementation at Runtime
http://www.eggheadcafe.com/tutorial...ng-wcf-service-implementation-at-runtime.aspx
 
Top