How can I get a custom text field (project level) to inherit data from
another custom text field (task level)???
another custom text field (task level)???
Jack Dahlgren MVP said:How is project ever going to know which task to roll up from?
With numbers you can roll up min, max, sum ... but with text what sort of
rule would you use? The first one alphabetically? Merge them altogether?
Take the first letter of each? Take the average? None of these approaches
would be very useful.
Because of this, there is no function to roll up task text fields to the
project level.
-Jack Dahlgren