In Project Server 2003, when the project is published, or
re-published, how can I make sure the actual work already
in the project is visible in the timesheet view? It seems
that once published and hours are entered, you can click
back through the calendar and check past hours entered.
However, if the project is for some reason re-published,
the "history" of actual hours disappears, and starts again
from the publish date.
Doea anyone know if there is something I can do to show
the entire actuals history, regardless of publishing. I
am publishing the same file every time.
Thanks,
Brian
re-published, how can I make sure the actual work already
in the project is visible in the timesheet view? It seems
that once published and hours are entered, you can click
back through the calendar and check past hours entered.
However, if the project is for some reason re-published,
the "history" of actual hours disappears, and starts again
from the publish date.
Doea anyone know if there is something I can do to show
the entire actuals history, regardless of publishing. I
am publishing the same file every time.
Thanks,
Brian