Publishing all tasks

C

Colin Anderson

One of our project managers is experiencing problems, when
he attempts to publish "All Information".
It seems that some of his resources cannot see new tasks
via Web Access, as though these tasks have not been
published properly.
If the PM selects individual tasks - he has tried with up
to 25 at once - everything seems to work as it should.

There are approx. 900 tasks in the project.

We are using Project Professional 2002 ans Project Server
2002.

Thanks in advance

Colin
 
S

Sarah

Colin,

Has your PM tried the option "Republish Assignments"? This is the
option that pushes the actual resource assignment information out to
the resources' My Tasks views.

Sarah
sarah_kiko@(removethis)cinfin.com
 