It appears to me, bsed on various tests, that a project plan is getting
published whenever it is closed in Project Pro. Is this true? I thought that
you either had to explicitly publish a project or take advantage of the auto
publish on save. I am not using the auto publish. I ran a test by sending
updated hours via a timesheet. I accepted all of the changes and updated the
project. I save the project. The changes are not visible in PWA or in OLAP
reports. That is what I expected. I then closed project pro without ever
publishing. All of the updated hours are now visible in Project center and
OLAP (after cube regen). I did not expect that. I thought the data was not
visible in PWA until it was published.
published whenever it is closed in Project Pro. Is this true? I thought that
you either had to explicitly publish a project or take advantage of the auto
publish on save. I am not using the auto publish. I ran a test by sending
updated hours via a timesheet. I accepted all of the changes and updated the
project. I save the project. The changes are not visible in PWA or in OLAP
reports. That is what I expected. I then closed project pro without ever
publishing. All of the updated hours are now visible in Project center and
OLAP (after cube regen). I did not expect that. I thought the data was not
visible in PWA until it was published.