J
John Sitka
Hi,
I'm in a situation where depending on which project is open or edited the
tasks are getting pushed twice.
That is if I edit publish from the MASTER project I get tasks in a PWA
hierarchical form
MASTER
- PROJECT 1
--SUMMARY TASK
---TASK
and
if I edit publish from PROJECT1 I get task hierarchy
PROJECT 1
-SUMMARY TASK
--TASK
Both task trees are visable when the resource logs in, duplicates? not
really...
So please share succssful editing/publishing procedure when using a MASTER,
SUB, SUB-SUB project set up.
I guess there are two cases
1.) where a Project Manager exploits a Master and he is Project Manager of
all SubProjects
2.) the Enterprise Manager uses the Master to gather all contributions from
the set of Progect Managers.
How to lock down one model or the other? Either by procedure or
configuration.
I'm in a situation where depending on which project is open or edited the
tasks are getting pushed twice.
That is if I edit publish from the MASTER project I get tasks in a PWA
hierarchical form
MASTER
- PROJECT 1
--SUMMARY TASK
---TASK
and
if I edit publish from PROJECT1 I get task hierarchy
PROJECT 1
-SUMMARY TASK
--TASK
Both task trees are visable when the resource logs in, duplicates? not
really...
So please share succssful editing/publishing procedure when using a MASTER,
SUB, SUB-SUB project set up.
I guess there are two cases
1.) where a Project Manager exploits a Master and he is Project Manager of
all SubProjects
2.) the Enterprise Manager uses the Master to gather all contributions from
the set of Progect Managers.
How to lock down one model or the other? Either by procedure or
configuration.