PWA 2007 Activity Task usage, not duration

D

DevourU

Anyone know how I can have an activity task collect usage without duration?
TIA!

-JS
 
D

Dale Howard [MVP]

DevourU --

Not possible. In an Activity plan, each task must have a Duration value.
Hope this helps.
 
Top