PWA 2007 My Tasks display - work in days

A

Astro Boy

I'm no doubt missing something obvious, but I don't see any way to change the
Remaining Work and Progress values on the My Tasks page in PWA 2007 to
display in hours, rather than days.

Work is in hours everywhere else. Has anyone run across the control which
changes it here?

Thanks!

AB
 
R

Ray McCoppin

You can edit the shared webpart settings, in the PWA settings you can set the
work format to hours.

Hope this helps.
 
A

Astro Boy

Genius! Thank you, Roy!

I'm so conditioned to controlling everything thru PWA admin, that I
completely forgot these are now SharePoint pages.

Thanks again!
 
A

Astro Boy

I meant to say "Thank you, RAY!" Sorry about that. I was so happy to find an
answer I momentarily lost the ability to read.
 