PWA 2007 - RBS structure in MSP Portfolio Analyzer(cube)

M

marko

In our organization we have set the RBS code structure based on company org.
The problem is that we can't wiev/connect the RBS field in the cube. Have any
suggestion?
 
D

Dale Howard [MVP]

Marko --

After creating the RBS outline code structure, you need to specify an RBS
value for each resource in the Enterprise Resource Pool. Did you do this?
In addition, your PM's must add resources to projects, assign the resources
to tasks, and then publish their projects. After the OLAP cube rebuilds the
next time, you should see the RBS outline code as a dimension in Portfolio
Analyzer views. Hope this helps.
 
M

marko

Dale --

first Thanks for your answer.
We have entered values in E. R. Pool for RBS and assign resources to tasks
in a project and publish to PWA. The problem is that in the Portfolio
Analyzer views we can't find the RBS dimension view but only the resource
name list. We would like to have this view of resources in a project grouped
like in RBS structure.

for example:
- under RBS group SALES we have this resources (Marko, Andrea, Francesco,...)
....
...
..
 
Top