J
Jennifer
We have two instances where actuals are showing up in the PWA actual work
column that were never entered and do not show up in the project plan even
after all time as been updated. I need to know how this happened and how to
correct the problem (remove the hours that were never entered and never
worked). What is even stranger is the number of actual hours for both people
are the exact same, 313.57h.
Thanks,
Jennifer
column that were never entered and do not show up in the project plan even
after all time as been updated. I need to know how this happened and how to
correct the problem (remove the hours that were never entered and never
worked). What is even stranger is the number of actual hours for both people
are the exact same, 313.57h.
Thanks,
Jennifer