PWA, assigned task status once task has been deleted...

C

Cynthia

We have published plans, with baselines, where we have
agreed upon changes to delete specific tasks. No matter
how we approach the delete process, we have an issue with
the PWA (STS) still sending reminders on the deleted
tasks. Additionally, while these tasks no longer appear
in the published project plan, the deleted tasks still
appear in the PWA of the assigned resources with "X"s in
the left column.

The only way I have found to correct this issue is to save
the plan to become a .mpp. Then thru clean up on the PWA
delete the published project and note the STS location.
Then import the corrected .mpp, go to STS change the
location back to the noted original.

Any ideas about how this could be prevented in the first
place, or an easier correction process?
 
D

Dale Howard

Cynthia --

Cancelled tasks show up on each user's timesheet with a big black X in the
indicators column. To remove those cancelled tasks from their timesheet,
each team member should select each cancelled task and then click the Hide
button. Hope this helps.
 
Top