PWA % comp VS hours worked

B

Bill

I have a client who decided in mid stream to change from hours worked to %
Complete. They made the change to the web access settings on the admin page
of project server. The problem is... all the user screens still show hours
worked instead of % Complete. Any ideas on how to fix this problem?

Bill
 
D

Dale Howard [MVP]

Bill --

You need to open every project and republish the assignments using
Collaborate - Publish - Republish Assignments. This will "push" the new
method of tracking to each user's timesheet in PWA, but will only impact
unstarted tasks. Any in-progress tasks will continue to use the former
method of tracking until they are completed. Hope this helps.
 