Marcus Pierce
Our project calendar (in Enterprise Global) is based on an 8 hour day, and
this works fine in Pro. Upon reviewing our plans via PWA, I noticed what
appears to be a conflict on the duration field--it seems like it is
considering a 6 hour day.
For example, the duration for Task #3 is 10 days 6/9 - 6/20 but the same
task viewed via PWA is 13.33 days while maintaining the 6/9 and 6/20
start/end dates.
Is there is a separate day definition setting unique to PWA - any ideas?
Thanks,
--Marcus